Revenue Assurance System — Delivery Portal

Shared view of the implementation plan, tasks, deliverables and open points for contract CA/SCM/IOT/01/2025-2026.

Loading

Contract record

Plan, milestones and deliverables follow Appendices 1 to 4 of the signed contract.
Contract signed23 Jun 2026
Inception meeting29 Jun 2026
M1 solution design signed off29 Jun 2026
Performance bondKES 164,646,570 · 21 Jul 2026
Licensee CEO briefing1 Sep 2026 · 8 licensees
Implementation window12 months from effective date

Critical path — licensee requirements to hardware

Everything downstream is waiting on step 2.

Phases

Progress is the share of tasks marked done in each phase.

Acceptance and payment milestones

Percentages of the supply, delivery, installation and configuration cost.

Governance and escalation